Separate a pilot, pre-stage, final sync and validation. Use observed transfer performance from the pilot to adjust the workload and notify users of expected changes. Check shared mailboxes, delegation and calendars alongside the primary mailbox data.
Prepare your inputs
Estimate total mailbox data, effective transfer speed, cutover window and mailbox count. Plan a pilot batch.
Worked example
A 500 GB migration at an effective 100 Mbps takes about 11.1 hours before throttling or overhead.
Review before you use the result
Confirm permissions, routing, retention and method in Microsoft 365 before scheduling cutover.
Microsoft mailbox migration documentation